Activities prior to the installation:

 • Inspection of Civil Work layout and status

 • Clarification of site responsibility during installation

 • Clarify Manpower, tools and machinery provided by Customer

 • Define ready for installations

 Commencement of Installation:

 • Installation of the Switchgear

 • SF6 handling

 • HV Test of the Switchgear with PD method

 • Installation of local boards, if freestanding

 • Cabling

 • Interlocking test

 • Test of control functions including a remote control interface

 • Test of Protection if integrated into the local control board

 Administration:

 • Weekly progress reporting to manufacturers head office

 • Reporting missing material, wrong design, deviation et cetera

 • Snag List negotiations on behalf of the manufacturer

 • Negotiations to obtain the Provisional Acceptance Certificate PAC

 • Support to obtain the Final Acceptance Certificate FAC.

 Worked on voltage level : 66/132/220/400 kV