Activities prior to the installation:
• Inspection of Civil Work layout and status
• Clarification of site responsibility during installation
• Clarify Manpower, tools and machinery provided by Customer
• Define ready for installations
Commencement of Installation:
• Installation of the Switchgear
• SF6 handling
• HV Test of the Switchgear with PD method
• Installation of local boards, if freestanding
• Cabling
• Interlocking test
• Test of control functions including a remote control interface
• Test of Protection if integrated into the local control board
Administration:
• Weekly progress reporting to manufacturers head office
• Reporting missing material, wrong design, deviation et cetera
• Snag List negotiations on behalf of the manufacturer
• Negotiations to obtain the Provisional Acceptance Certificate PAC
• Support to obtain the Final Acceptance Certificate FAC.
Worked on voltage level : 66/132/220/400 kV